Offsite Project Team: Kerri Goergen-Doll, Preciosa Martinez, Laura Ramos and Elizabeth Nielsen and Marty Brown.
Project will be presented and shared out at an admin briefing in February.
Current Timeline and Impacts
-Construction on ‘Nypro Building’ through April
-Deselection on the first floor and at current offsite
-Spacesaver will lay track and install shelving for compact storage (May/June)
-Move of materials to new offsite storage (Late May/June)
-Settle into new space, figure out processes, move of all other items (Press, SCARC)
Current basic overview of the project timeline: