Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

-This refers to motors that move the carriages along the rails, and bearings on which they glide.
-Servicing these means the shelving units will operate more smoothly and reliably in terms of mechanics. 

History:

First section of compact shelving (small section on east of floor) upgraded 2018 with display screen controls. 
The second bank of compact shelving on the 1st floor was upgraded, the motors serviced the week of August 22, 2022. The electronic components are backordered and expected to come in early January 2022. 

Status: Repairs and Upgrades In Progress, Planning Future Schedule
Issues with motors and bearings have been increasing in 2022. Repairs are ongoing.

Originally scheduled for January 2023. 
NEXT section slated for updating on the first floor is a bank of 8 long carriages next in line from the west end of the floor in January February 2023.

For each year going forward, the next sections controls and motors will be upgraded as budget allows.

For more detailed information refer to the Planning Document: https://docs.google.com/document/d/1JNprgpPWRU9U8xiaVMfkSxvmXUArWw1m7EBoj4Mj_7o/edit?usp=sharing 

Contacts: Laura Ramos, Rachel Burgess, and Julie Judkins.
Vendor: Spacesaver Specialists Contact: Matt Reader, Stan Ruiter