Library Facility and Space Projects Timeline
A summary list of completed, planned, and expected space and facility projects in the library by year with status and key individuals listed.
Library Facilities & Space Projects Timeline
2022
Offsite Exterior Repairs – Complete
3rd Floor Open Study – Complete
Liebert for SCARC – Complete
Autzen Flexibility – Complete
Compact/Spacesaver Shelving – In progress/planning
LED Lighting (Basement, 1st, 3rd, 5th, 6th Floors) – Ongoing
Library Plaza – Complete
Concierge Desk – Complete
Offsite Environmental Monitoring – Ongoing
2023
LEAD Desk – Complete | Rachel Burgess, Uta Hussong-Christian
Printers – Committee, complete | Erin Kooyman, Dave Manela, Margaret Mellinger, Rachel Burgess, Kristin Swetland
Compact Shelving – Planning, in progress | Laura Ramos, Rachel Burgess
Staff Lounge Interior – LEA, committee, on hold
LED Lighting Work – Ongoing
ATT/Antennae Project – Complete, in progress | Campus Planning, Rachel Burgess
Planning for Learning Commons – Committee formed | Rachel Burgess, Richenda Hawkins, Dave Manela, Beth Filar-Williams, Kristin Swetland, Diana Castillo
Study Room Locks – Complete | Lucinda Amerman
2024
4th Floor Office Space – Complete/committee | Angela Haney, Rachel Burgess, Admin Dept, Margaret Mellinger, Dave Manela
Learning Commons – In progress/committee | Richenda Hawkins, Rachel Burgess, Diana Castillo, Dave Manela, Beth Filar-Williams, Kristin Swetland
Windows: Shades & Film – In progress, multi-year
HVAC System Controls Investigation & Upgrade – In progress
Compact Shelving Offsite – Complete
Autzen Revisit – On hold (capacity limits)
Carpet Investigation – In progress
Maps Compression – Complete | Rachel Burgess, Laura Ramos, Jane Nichols, Brad Engelbert
3rd Floor Tutoring (Mole Hole/Worm Hole) – Complete (Stage 1) | Rachel Burgess, Diana Park, Margie Haak, Fred DeAngelis
Barnard Classroom Upgrades - Complete | Rachel Burgess, SCARC
2025
Carpet – Main Floor – Pending (Summer 2025) | Rachel, LC Committee
Carpet – 5th & 6th Floor Hallways – Spring 2025 | Rachel
Learning Commons – In progress/committee, completion Summer 2025
Solar Panels at Guin – Negotiation stage | Campus Planning, Guin, Office of Sustainability
Window Films & Shades – Spring 2025 | Rachel
Archival Scanning Lab – Spring 2025 | Rachel, Julie, Brian
Space Plan for 10 Years – December 2025, in progress | Rachel, consultant/committee?
Wayfinding Systems – Fall 2025–Summer 2026 | Rachel, Robin, Sagan, Beth, Rep for RAS, Rep for LEAD
PA System Upgrade – Spring 2025
2026–2027
Maps Room Recarpet & Rethink – In progress/committee | Rachel Burgess, Jane Nichols, Brad, Laura Ramos, Diana Park, Ashley
Compact Shelving – In planning | Rachel Burgess, Laura Ramos
Sensory Spaces – Assessment phase
Sustainable & Accessible Restrooms – In progress | Rachel Burgess, Campus Planning & Architecture
Roof – Campus Planning
Alarm System/Fire Panels – Pending
Tutoring Space Rethink – Pending/committee
Elevators – Advocacy stage
3rd Floor Staff Space – Carpet materials purchased | Rachel Burgess