Phases 3 and 4 - OSUL Website Refresh Project

Task

Who is involved

Start date

End date

Comments

Task

Who is involved

Start date

End date

Comments

PHASE 3 Implementation (LIT) August 2024 - January 2025

MAC final deliverables received, Kick off meetings for LIT team

Beth Shields, Kenna Warsinske, Corey Gillen, Christa Wright, Christian Flores

August 15, 2024

 

UIT consultation as needed.

Set up staging server and production servers

Ryan, Kenna, Corey

 

08/30/2024

 

Set up GitHub Project Board

LIT team

 

8/30/2024

Talk about what needs to be built first, what will need additional research is needed.

Initial Accessibility Review

Kenna, Beth

August 2024

08/30/2004

Meet with OSU digital accessibility staff

Initial meetings with department representatives

Beth

August 2024

09/04/2024

Admin, R&L, Branches, LEAD, SCARC, RAS, Press

Follow up meetings will be scheduled as needed.

Complete content strategy analysis

Beth

08/13/2024

09/06/2024

MAC Wireframes: https://bit.ly/4clZEMx

MAC Architecture: https://drive.google.com/drive/u/0/folders/0ALZ5TLQuXApZUk9PVA

Identify and create reusable page components

Kenna, Corey

August 2024

09/13/2024

 

Page Builds

Christa, Christian, Margaret, Beth

09/16/2024

 

Build structure of pages using the reusable components

Start with Profile Pages, Main site pages

Build unique components

Kenna, Corey

09/16/2024

10/11/2024

Unique Components: Hours, Events, Search, Maps

Build headers

Kenna, Corey

09/16/2024

10/11/2024

 

Build footer

Kenna, Corey

09/16/2024

10/11/2024

 

Add content to pages

All

10/14/2024

 

 

Website Guidelines 

Beth and Margaret

 

 

 

Test new websites

Using MAC tests, LIT staff and others

 

 

Meet usability and accessibility standards

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Launch new sites

OSULP, Guin, Cascades

 

 

Launch: December 20, 2024

 

PHASE 4 Maintenance (LIT and others) January 2025

Create Web Team

LIT is proposing that all departments will have a point person on the Web Team (subject to LAMP conversation and approval)

 

 

The point person will be trained to work with web pages, to help others in their departments.  They will bring issues and ideas to quarterly meetings. 

Train Web Team

LIT and Web Team

 

 

Using the documentation (technical and visual standards )

Schedule quarterly meetings

Web Team

 

 

To discuss any issues with creating and maintaining pages.  To help plan for any larger change or enhancement. 

Devise processes for maintenance and enhancements

LIT and Web Team

 

 

Clearly define who is responsible for maintenance and the document the processes for deciding on major changes to the site (s).